Wednesday, 29 May 2013

Some Major Developments

Hi, it's been quite a while since I updated the blog so I thought it would be a good time to do so now that some things have happened recently.

As you can see from the walkthrough below, the roof is now nearly finished, and the inside of the roof is almost fully insulated. This week has been a major milestone in the project because the internal structural work has started. We've had some of the people from Studio People on site since yesterday and they've begun the work of setting out and preparing certain things. Their first job (installing Cellotex insulation in the roof space) is now almost completed and they can soon begin the job of creating the wooden frame structure within the live room and control room. After speaking to them today they have explained that the ceilings in both rooms will be nice and high, much higher than they would expect to be able to give in a 'home studio'. I'll take this as a compliment as this will be much more than a 'home studio'. I'm looking forward to seeing how it all takes shape.

We are in the process of having a new website made for me by Matt Thomas (http://www.mattthomas.co.uk) and once it is totally finished we'll put it out there properly, for now it is working like a blog and can be seen here www.skyhammerstudio.com.

This week marked the announcement that the very excellent Chris Fielding (www.chrisfielding.co.uk/news) will be moving into the studio once it is completed and will work here as producer. Chris is a great guy and is just simply excellent at what he does. He has worked on every release that we (Conan) have put out and through that we have built up a friendship and also a professional understanding and so therefore when he called me to ask if he could move to the studio, I didn't have a very difficult decision to make. You can see the scope of the work he has done so far on his website and it can come as no surprise that he is very well respected within the realms of music and music production. Initially I was going to have a go myself and build up my skills over time while hopefully building up the studio itself. Now with Chris here I can follow a different path and while the studio grows I can concentrate on one or two other projects I have rattling round my head while also committing time to the studio alongside Chris.

So things are going well so far, we have a 3d walkthrough of the studio on the way and I will upload that to the website soon.

The studio will be ready in early August 2013, we will soon be ready to take bookings. In the first instance you should email us on skyhammerstudio@gmail.com but we will have an email setup at the domain soon enough.

Thanks for reading...... Here's the latest walkthrough.


Friday, 17 May 2013

Video Walkthrough - 13th May 2013

Here is a short video showing the studio during the construction phase. This video was taken on the 13th May 2013




Saturday, 11 May 2013

More Progress

Hi all

So it looks like we have a two man team pretty much permanent on the studio now, and it is showing in the amount of progress we have had.

This last week we have got the internal blockwork (forming the acoustic barrier around the live room) up to lintel height and the old external wall (and supporting wall underneath) has been removed so that the studio is now fully open.

It looks a mess right now, but it is an active building site and it's really cool to see it taking shape the way it is.

Will probably do a video walk through next I think.






Tuesday, 7 May 2013

Closer and Closer...........

Been a bit busy with a few shows recently so haven't been able to update, but things are moving on nicely.

The shell of the building has now been made good and the only current way into the building is through the main doorway. The garage door has been removed and has been bricked up.

The biggest obstacle we faced was to do with the internal walls. There was one stretching the whole width of the building that was holding up some of the roof joists. This has now been removed and will be replaced by a similar wall about two feet further into the 'control room' space. There was quite a lot of rubble to move and once that was done the foundations were made and concrete poured and the first runs of brick were put in.

As I type the builder has put two extra men onto the job today to begin knocking down the other internal wall so that we can prop it up with steel, then remove all the walls below it - this will open up the inside of the building 100% and will make it ready for the studio designers (The Studio People) to come in and do their magic. The brickwork that is the 'internal acoustic barrier' around the live room has now begun and can be seen on the pics below. The 'before' and 'after' pics on the removal of the existing internal wall are below also.

The studio accommodation is pretty much finished and we are very happy with it. It comprises of two bedrooms (each sleeping a maximum of 4 people), a living room (with Freeview TV and comfortable seating), a kitchen and a shower / toilet room. It has WIFI, is secure by way of its own secure entrance, and is quiet and cozy due to the central heating and double glazed windows. We had Bongripper and Humanfly stay there recently while we (Conan) were on tour with them both and it was great. It's nice and quiet at that end of the house too so it will be a peaceful environment for them.